The company “Pozeminiai darbai” has accomplished obligations of the won project “Development of the Water Supply and Wastewater Networks in Jurbarkas Municipality” earlier than it was required by the public tender. General Manager of the company, Raimondas Baikstys states that the crisis failed to put a spoke in the wheel to complete the project.
The value of the project is 11,690,073.95 Lt. During the development of the water supply and wastewater networks, a number of gravity pipelines, pressure pipelines, pump houses, household connections, water supply networks, and household water supply connections was constructed. Overall, 12 136 meters of networks were built.
2009 06 16