In 2012 “Pozeminiai darbai” AB successfully completed several large-scale heat supply network construction projects: “Modernization of the heat supply infrastructure in Taurage . 2nd stage”, “Increasing reliability of Elektrenai heat supply infrastructure” and “Reconstruction of the heat supply networks in Elektrenai”.
The project in Elektrenai needed to be completed before the heating season. For this reason the work was finished in a very short time – less than two months. The project was supervised by Vytautas Jasaitis. The total length of the pipes network was 2100 meters.